    e-mail from a Eugene subscriber (I don't know him) today:

    <<I was surprised to see construction activity (excavation) today Saturday.

    A construction person came over to chat.

    Some tidbits...

    K&E Excavation was averaging 750 cubic yards dirt removal per hour yesterday (60-75 dump truck loads per hour out), and the trucks were also bringing in gravel fill. !!!!

    The track, which the trucks have using as a convenient highway, will be removed in ~ 1 week.

    Pilings will start to go in in ~ 2 weeks.

    Your Hayward Field construction site whisperer.....>>

    Leave a comment:


  • lonewolf
    replied
    Originally posted by Conor Dary View Post
    That makes sense...also saves time...The infield hasn't changed either...

    Though with all the trucks driving over it I wonder what it will be like...
    My first thought..

    Leave a comment:


  • Conor Dary
    replied
    That makes sense...also saves time...The infield hasn't changed either...

    Though with all the trucks driving over it I wonder what it will be like...

    Leave a comment:


  • gh
    replied
    Originally posted by Conor Dary View Post
    It appears they plan to keep the track... They actually washed it down today... I presume they will resurface it...
    my guess/bet is that it's resurfaced in late '20 so that there's a brand-new state-of-the-art oval in place for the WC. i suspect it has been many a year since a WC wasn't staged on an oval that hadn't been redone in the previous "year"